Wind Farm Senden

Windpark Senden-Bösensell

2 Enercon-160 EP5 E3 wind turbines, with a hub height of 160,0 and a capacity of 5,56 MW each, will be erected in Bösensell district of Senden.

Commissioning: 2024
Manufacturer: Enercon GmbH
Turbines: 2 x Enercon-160 EP5 E3
Output: 5.56 MW
Hub height: 160 m
Rotor Ø: 160 m

2 Enercon 160 EP5 E3 wind turbines with a hub height of 160 m and a capacity of 5.56 MW each will be erected in Bösensell, in the municipality of Senden.

Current Operations:

Concrete tower components are being delivered to WTG 2. Sunbelt Rentals GmbH is laying the temporary Trakways around the wind farm. Simultaniosly, cables lines are being layed between the wind turbines and the substation.

Completed Operations:

Both foundations have been re-covered with earth.

Roadworks: W. Koldewei GmbH  27252 Schwaförden
Vibro-compaction: Menard GmbH 44807 Bochum
Foundation: Max Bögl Bauservice & Co KG, 92369 Sengenthal
HSE: Thore Lindemann, 27245 Barenburg
Cables / Lines: DUS Kabelmontage, 26835 Hesel
Trakway: Sunbelt Rentals, 74248 Ellhofen

WEA 1
1.  KW  3  > Crane site compaction test completed.
2. KW   4 > Subbase concrete layer finished.
3. KW   5 > Foundation reinforcement cage completed.
4. KW   7 > Casting of the foundation.
5. KW   7 > Foundation castion completed.
6. KW   8 > Covering the with foundation with soil

WEA 2
1. KW  3 > Crane site compaction test completed.
2. KW  4 > Subbase concrete layer finished.
3. KW  5 > Foundation reinforcement cage completed.
4. KW  6 > Casting of the foundation.
5. KW  7 > Covering the with foundation with soil.
6. KW  9 > Delivery of tower components

 

 