Wind Farm Senden

Windpark Senden-Bösensell
2 Enercon-160 EP5 E3 wind turbines, with a hub height of 160,0 and a capacity of 5,56 MW each, will be erected in Bösensell district of Senden.
Commissioning: 2024
Manufacturer: Enercon GmbH
Turbines: 2 x Enercon-160 EP5 E3
Output: 5.56 MW
Hub height: 160 m
Rotor Ø: 160 m
2 Enercon 160 EP5 E3 wind turbines with a hub height of 160 m and a capacity of 5.56 MW each will be erected in Bösensell, in the municipality of Senden.
Current Operations:
Construction of the main access roads, curves and crane site areas has begun during the 33 KW.
Roadworks: W. Koldewei GmbH 27252 Schwaförden
WEA 1
1. KW 36 > Roadworks and crane site construction have been completed.
WEA 2
1. KW 39 > Roadworks and crane site construction have been completed.