Wind Farm Senden

Windpark Senden-Bösensell

2 Enercon-160 EP5 E3 wind turbines, with a hub height of 160,0 and a capacity of 5,56 MW each, will be erected in Bösensell district of Senden.

Commissioning: 2024
Manufacturer: Enercon GmbH
Turbines: 2 x Enercon-160 EP5 E3
Output: 5.56 MW
Hub height: 160 m
Rotor Ø: 160 m

2 Enercon 160 EP5 E3 wind turbines with a hub height of 160 m and a capacity of 5.56 MW each will be erected in Bösensell, in the municipality of Senden.

Current Operations:

Construction of WTG 1 & 2 has been completed. The MaxiKraft LR 1100 crane is now moving to WTG 1 and will be re-assembled there in the coming days. Sunbelt Rentals GmbH is removing the temporary Trakways that are lining the access roads and recultivation of the surrounding ground will begin shortly. The DUS company, is now laying the last hundred meters of cable between the wind turbines and the substation.

Completed Operations:

Both foundations have been re-covered with earth.

Roadworks: W. Koldewei GmbH  27252 Schwaförden
Vibro-compaction: Menard GmbH 44807 Bochum
Foundation: Max Bögl Bauservice & Co KG, 92369 Sengenthal
HSE: Thore Lindemann, 27245 Barenburg
Cables / Lines: DUS Kabelmontage, 26835 Hesel
Trakway: Sunbelt Rentals, 74248 Ellhofen

WEA 1
1.  KW   4 > Subbase concrete layer finished..
2. KW    5 > Foundation reinforcement cage completed.
3. KW    11> Delivery of tower segments.
4. KW   13> Concrete tower construction complete.
5. KW   21> Final assembly begins.
6. KW   24> Tower construction complete..

WEA 2
1. KW   7 >  Covering the foundation with soil.
2. KW  9 >  Delivery of tower segments.
3. KW 13 > Concrete tower construction complete.
4. KW 14 > Delivery of Nacelle, rotorblades and generator.
5. KW 17 > Final assembly begins.
6. KW 20> Tower construction complete.

 

 