Wind farm Altenmarhorst

Wind park Altenmarhorst

We are constructing 19 Enercon E-175 EP5 E2 wind turbines with a hub height of 162 m and an output of 7.0 MW in the Altenmarhorst district of Twistringen, Diepholz district.

Commissioning: 2027
Manufacturer: Enercon
Number: 19x Enercon E-175 EP5 E2
Nominal output: 7.0 MW
Hub height: 162 m
Rotor: 175 m

We are constructing 19 Enercon-175 EP5 E2 wind turbines with a hub height of 162 m and an output of 7.0 MW in the Altenmarhorst district of Twistringen, Diepholz district.

Current status:

Lüers began construction of the access roads and crane sites in calendar week 34, and the work is expected to be completed in early 2026. At the same time, the construction site is being monitored by environmental, soil protection, and archaeological measures.

Completed work at the wind farm:

The cutting back of trees and shrubs was carried out in September-October 2025 by Belke Naturteam from Schwaförden. We would like to thank Belke Naturteam for their excellent cooperation and the impeccable execution of the work.

The following companies were involved during the construction period:

Development/road construction:
Lüers GmbH, 27239 Twistringen

Archaeological construction supervision
Denkmal 3D, 49377 Vechta

Environmental construction supervision
Stadtlandkonzept, 33824 Werther

WTG 1
1st week > 48 Excavation of crane site.

WTG 2
1st week > 41 Excavation of crane site.

WTG 3
1st week 47 > Excavation of crane site.

WTG 4
1st week 40 > Excavation of crane site.

WTG 5
1st calendar week 47 > Excavation of crane site.

WTG 6
1st calendar week 43 > Excavation of crane site.

WTG 7
1st calendar week 40 > Excavation of crane site.

WTG 8
1st calendar week 40 > Excavation of crane site.

WTG 9
Week 40 > Excavation of crane site.

WTG 10
Week 40 > Excavation of crane site.

WTG 11
Week 40 > Excavation of crane site.

WTG 12
Week 47 > Excavation of crane site.

WTG 13
Week 40 > Excavation of crane site.

WTG 14
Week 39 > Excavation of crane site.

WTG 15
Week 34 > Excavation of crane site.

WTG 16
Week 47 > No activities currently

WTG 17
Week 47 > No activities currently

WTG 18
Week 47 > No activities currently

WTG 19
Week 47 > No activities currently