Wind farm Hustedt

Wind farm Hustedt

We are constructing one Enercon-175 EP5 wind turbine with a hub height of 139 m and an output of 6 MW in Hustedt, Bruchhausen-Vilsen municipality, Martfeld district.

Commissioning:
Manufacturer: Enercon GmbH
Number: 1 x Enercon-175 EP5
Nominal output: 6 MW
Hub height: 139 m
Rotor diameter: 175 m

We are constructing one Enercon-175 EP5 wind turbine with a hub height of 139 m and an output of 6 MW in Hustedt, Bruchhausen-Vilsen municipality, Martfeld district.

Current status:
Tower construction work was completed in calendar week 46. All tower components and all three rotor blades were successfully delivered in calendar week 41. Tower construction is now continuing and is expected to be completed in calendar week 45. The first tower segment was installed in calendar week 18. The parts of the HST tower are currently being pre-assembled. Tower construction will begin on April 28, 2025, and the first tower segment will be installed. Construction of the foundation was completed in week 11, and the tower parts will now be delivered. In calendar week 8, DTZ Betonbau began construction of the anchor cage. The expansion of the access roads, access radii, and crane sites began in the second week of 2025.Road construction: W. Koldewei GmbH, 27252 Schwaförden
Foundation construction: DTZ Betonbau, 06895 Zahna-Elster

WTG 1
Week 10 > Reinforcement installation.
Week 10 > Foundation construction completed.
Week 10 > Foundation construction completed.
Week 18 > From April 28: Tower construction.
Week 39 > Final assembly: Delivery of tower components.
Week 46 > Tower construction completed.

More info

You can find data and photos relating to our projects here.

You can find an overview of the latest news under News