Wind Farm Martfeld II
Current status:
Max-Bögl will begin construction of the foundations in calendar week 6. Koldewei began work on the access roads and crane sites in calendar week 48. The removal of topsoil, including archaeological, soil protection, and environmental monitoring, is expected to be completed in early February 2026.
Road construction: Koldewei GmbH, 27252 Schwaförden
Archaeological monitoring: ArcheoFirm, 30916 Isernhagen
Environmental monitoring: StadtLandkonzept, 33824 Werther
Wind turbine 1
Week 51 > Installation of fill sand.
WEA 2
1st week 30 > Installation of geogrid/mineral mixture in crane area.
WEA 3
1st week 49 > Installation of geogrid/mineral mixture in crane area.
WEA 4
1st week 49 > Installation of geogrid/mineral mixture in crane area.
Wind turbine 5
Week 50 > Installation of STS layer.
Wind turbine 6
Week 47 > Installation of geogrid/mineral mixture in crane area.
Week 51 > Installation of cable conduits.
Week 03 > Installation of STS layer.
More info
You can find an overview of the latest news under News.