Wind Farm Harsewinkel-Kattenstrot

Wind Farm Harsewinkel-Kattenstrot
We are constructing two Enercon-160 EP5 E3 wind turbines with a hub height of 166 m and an output of 5.56 MW in the Kattenstrot district of Harsewinkel, in the district of Gütersloh.
Commissioning:
Manufacturer: Enercon GmbH
Number: 2 x Enercon-160 EP5 E3
Nominal output: 5.56 MW
Hub height: 166 m
Rotor diameter: 160 m
We are constructing two Enercon-160 EP5 E3 wind turbines with a hub height of 160 m and an output of 5.56 MW in the Kattenstrot district of Harsewinkel, in the district of Gütersloh.
Current status:
The first section of the tower construction on wind turbine 2 has been completed. The Gertzen LR 1750 large crane is currently being erected on wind turbine 1. Tower construction on this turbine is scheduled to begin in calendar week 43. The foundation work on wind turbine 1 has been completed and the reinforcement installation on wind turbine 2 is almost complete. At WEA 1, the reinforcement work has been completed and concrete was poured on June 26, 2025. Reinforcement work is currently being carried out on WEA 2. The expansion of the access roads, access radii, and crane sites began in calendar week 16 of 2024.
Road construction: W. Koldewei GmbH, 27252 Schwaförden
Tower construction: Max Bögl, 93269 Sengenthal
Wind turbine 1
1. Week 25 > Reinforcement installation completed.
2. Week 26 > Concrete pouring.
3. Week 27 > Foundation construction completed.
4. Week 37 > Delivery of tower components.
5. Week 43 > Erection of the LR 1750 large crane.
6. Week
Wind turbine 2
1. Week 25 > Installation of sub-base layer completed.
2. Week 26 > Reinforcement installation completed.
3. Week 36 > Delivery of tower components.
4. Week 41 > Tower construction has begun.
5. Week 42 > First section of tower construction completed.
6. Week