Wind Farm Albringhausen II

Wind Farm Albringhausen II

In 2022 a total of 10 Enercon 160 EP5 E3 wind turbines with a hub height of 166 m and a capacity of 5.56 MW each, will be erected in Albringhausen, District of Bassum.

Commissioning: 2023
Manufacturer: Enercon PLM GmbH
Turbines: 10x Enercon 160 EP5 E3
Output: 5.56 MW
Hub Height: 166 m
Rotor Ø: 160 m

A total of 10 Enercon 160 EP5 E3 wind turbines with a hub height of 166 m and a capacity of 5.56 MW each will be erected in Albringhausen, District of Bassum. Simultaneously, 13 Enron 1.5 wind turbines are being dismantled.

 

Current Operations:

Two LR 11000 cranes have arrived onsite, one belonging to the Hueffermann company and the second to the Wasel company. Currently, the two cranes are erecting WTG 4 and WTG 5 repectively. WTG 6 has been completed and is now in the process of being connected to the local substation.

Simultaneously, the DUS Kabelmontage company is laying the cables to and from the substation.

In week 33, a second LM 1750 crane has arrived started to assemble tower 5.

Completed Operations at the Wind Park:

The concrete tower assembly phase has been completed.

The Max-Bögl company has completed the construction of the foundations.

The pruning of trees and shrubs was carried out in January and February 2022 by the GaLaBau-Nietfeld company from Staken/Steyerberg. Many thanks to the Nietfeld company for their solid partnership and the impeccable execution of their work.

The dismantling of the 13 old Enron 1.5 wind turbines was completed during the 15th calendar week.

The demoliton of the 13 old Enron 1,5 Wind turbine foundations was complete on 14 April 2022. We would like to thank the Reisch Sprengtechnik GmbH company for their professionalism and impeccable work.

During week 13, the Koldwei company started with roadworks and the construction of crane parking areas. All road works were completed in May.

Foundation Builders: Max- Bögl 92369 Sengenthal
Tower Assembly: Max- Bögl 92369 Sengenthal
Tower Assembly: Wasel GmbH 50126 Bergheim
Tower Assembly: Hüffermann Krandienst 21683 Stade
Roadworks: W. Koldewei GmbH  27252 Schwaförden
Demolition & Recycling: Wiechert GmbH  49453 Hemsloh
Blasting Operations: Reisch Sprengtechnik GmbH  86974 Apfeldorf

 

WEA 1
1.   KW 36 > Anchor cage foundation construction in progress.
2.   KW 37 > Cement foundation completed.
3.   KW 37 > Foundation landscaping and earthworks.
4.   KW 41 > Delivery of concrete tower components.
5.   KW 42 > Tower assembly has commenced.
6.   KW 43 > Concrete tower assembly has been completed.

WEA 2
1.   KW 34 > Anchor cage foundation construction in progress.
2.   KW 35 > Foundation landscaping and earthworks.
3.   KW 38 > Delivery of concrete tower components.
4.   KW 39 > Tower assembly has commenced.
5.   KW 41 > Concrete tower assembly has been completed.
6.   KW 48 > Delivery of blades, generator and nacelle.

WEA 3
1.   KW 36 > Cement foundation completed.
2.   KW 37 > Foundation landscaping and earthworks.
3.   KW 39 > Delivery of concrete tower components.
4.   KW 40 > Tower assembly has commenced.
5.   KW 42 > Concrete tower assembly has been completed.
6.   KW 45 > Delivery of blades, generator and nacelle.

WEA 4
1.   KW 33 > Delivery of concrete tower components.
2.   KW 34 > Tower assembly has commenced.
3.   KW 35 > Concrete tower assembly has been completed.
4.   KW 40 > Delivery of blades, generator and nacelle.
5.   KW 43 > Delivery & assembly of LR 11000 Hueffermann crane.
6.   KW 46 > Tower, nacelle and rotor blade assembly in progress.

WEA 5
1.   KW 34 > Tower assembly has commenced.
2.   KW 35 > Concrete tower assembly has been completed.
3.   KW 36 > Delivery & assembly of LR 11000 Wasel crane.
4.   KW 40 > Delivery of blades, generator and nacelle.
5.   KW 43 > Tower, nacelle and rotor blade assembly in progress.
6.   KW 48 > Wind turbine assembly completed.

WEA 6
1.   KW 32 > Tower assembly has commenced.
2.   KW 33 > Concrete tower assembly has been completed.
3.   KW 38 > Delivery of blades, generator and nacelle.
4.   KW 38 > Delivery & assembly of LR 11000 Hueffermann crane.
5.   KW 42 > Wind turbine assembly completed.
6.   KW 42 > Crane will be disassembled and moved to WEA 4.

WEA 7
1.   KW 33 > Cement foundation completed.
2.   KW 34 > Foundation landscaping and earthworks.
3.   KW 35 > Delivery of concrete tower components.
4.   KW 36 > Tower assembly has commenced.
5.   KW 38 > Concrete tower assembly has been completed.
6.   KW 44 > Delivery of blades, generator and nacelle.

WEA 8
1.   KW 32 > Cement foundation completed.
2.   KW 34 > Foundation landscaping and earthworks.
3.   KW 34 > Delivery of concrete tower components.
4.   KW 35 > Tower assembly has commenced.
5.   KW 36 > Concrete tower assembly has been completed.
6.   KW 42 > Delivery of blades, generator and nacelle.

WEA 9
1.   KW 31 > Cement foundation completed.
2.   KW 32 > Foundation landscaping and earthworks.
3.   KW 33 > Delivery of concrete tower components.
4.   KW 35 > Tower assembly has commenced.
5.   KW 36 > Concrete tower assembly has been completed.
6.   KW 41 > Delivery of blades, generator and nacelle.

WEA 10
1.   KW 34 > Cement foundation completed.
2.   KW 35 > Foundation landscaping and earthworks.
3.   KW 36 > Delivery of concrete tower components.
4.   KW 37 > Tower assembly has commenced.
5.   KW 38 > Concrete tower assembly has been completed.
6.   KW 42 > Delivery of blades, generator and nacelle.

 

More info

Data & photos of our projects can be found here.

News in the overview you will find under news.