Wind Farm Albringhausen II

Wind Farm Albringhausen II

In 2022 a total of 10 Enercon 160 EP5 E3 wind turbines with a hub height of 166 m and a capacity of 5.56 MW each, will be erected in Albringhausen, District of Bassum.

Commissioning: 2023
Manufacturer: Enercon PLM GmbH
Turbines: 10x Enercon 160 EP5 E3
Output: 5.56 MW
Hub Height: 166 m
Rotor Ø: 160 m

A total of 10 Enercon 160 EP5 E3 wind turbines with a hub height of 166 m and a capacity of 5.56 MW each will be erected in Albringhausen, District of Bassum. Simultaneously, 13 Enron 1.5 wind turbines are being dismantled.

 

Current Operations:

Construction of access roads, intersections and crane sites started at the end of January.

In April, foundation debris are being collected and being reutilized for roadways and crane areas.

Completed Operations at the Wind Park:

The pruning of trees and shrubs was carried out in January and February 2022 by the GaLaBau-Nietfeld company from Staken/Steyerberg. Many thanks to the Nietfeld company for their solid partnership and the impeccable execution of their work.

The dismantling of the 13 old Enron 1.5 wind turbines was completed during the 15th calendar week.

The demoliton of the 13 old Enron 1,5 Wind turbine foundations was complete on 14 April 2022. We would like to thank the Reisch Sprengtechnik GmbH company for their professionalism and impeccable work.

During week 13, the Koldwei company started with roadworks and the construction of crane parking areas. All road works were completed in May.

Roadworks: W. Koldewei GmbH  27252 Schwaförden
Demolition & Recycling: Wiechert GmbH  49453 Hemsloh
Blasting Operations: Reisch Sprengtechnik GmbH  86974 Apfeldorf

 

WEA 1
1.    KW 10 > Start 10.02.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

WEA 2
1.    KW 07 > Start 14.02.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

WEA 3
1.    KW 08 > Start 21.02.2022 site development / crane site construction.
2.    KW 21 > Site development and raodworks have been completed.

WEA 4
1.    KW 12 > Start 22.03.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

WEA 5
1.    KW 12 > Start 21.03.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

WEA 6
1.    KW 14 > Start 04.04.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

WEA 7
1.    KW 18 > Start 02.05.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

WEA 8
1.    KW 05 > Start 31.02.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

WEA 9
1.    KW 09 > Start 28.02.2022 site development / crane site construction.
2.    KW 21 > Site development and raodworks have been completed.

WEA 10
1.    KW 11 > Start 14.03.2022 site development / crane site construction.
2.   KW 21 > Site development and raodworks have been completed.

 

More info

Data & photos of our projects can be found here.

News in the overview you will find under news.