Wind farm Bruchhagen-Nendorf

Wind farm Bruchhagen-Nendorf

In 2021, a total of 14 Enercon E-126 EP3 wind turbines with a hub height of 134.35 m and a capacity of 4.0 MW each, were built and put into commission in Bruchhagen, Flecken Steyerberg, Stolzenau, district of Nienburg.

Commissioning:
Manufacturer: Enercon GmbH
Quantity: 14 x Enercon E-126 EP3
Nominal power: 4 MW
Hub height: 134.35 m
Rotor Ø: 127 m

A total of 14 Enercon E-126 EP3 wind turbines with a hub height of 134.35m and a capacity of 4.0 MW each were completed and commissioned in Bruchhagen, Flecken Steyerberg, district of Nienburg.

Current work at the wind farm:

Due to considerable road damage and in consultation with the local communities, approx. 11.9 km of roads were repaved. The Koldewei company carried out the work.

The following companies were active during the construction period:

Surveying:
ÖBVI Lambers & Ostendorf, 49406 Barnstorf

Archaeological site supervision:
ArchaeoFirm Poremba & Kunze GbR, 30916 Isernhagen, Germany.

Pedological site supervision:
GEONOVO GmbH, 26789 Leer

Environmental site supervision:
Certified biologist Detlef Gerjets, 26446 Friedeburg, Germany

Ground surveyor:
Engineering geology Dr. Lübbe, 49377 Vechta

SiGeKo (Occupational Safety):
Tobias Pohl, 27245 Bahrenborstel

Site development/road construction:
Luers GmbH, 27239 Twistringen
Wiechert GmbH, 49453 Hemsloh

Subsoil reinforcement:
Bauer Spezialtiefbau GmbH, 86529 Schrobenhausen, Germany

Foundation construction:
Meyer Sonderbau GmbH, 29525 Uelzen, Germany

Dewatering:
Koop Wasserbau GmbH, 48455 Bad Bentheim, Germany

Tower construction:
Oehm GmbH & Co.KG, 49716 Meppen, Germany

Temporary access panels:
LiveTrakway GmbH, 74632 Neuenstein, Germany

Substation:
WT Energiesysteme, 01587 Riesa, Germany

Undereground utilities construction
DUS Kabelmontage GmbH & Co. KG, 26835 Hesel