Lügde Wind Farm

Lügde Wind Farm

A total of 11 Enercon-160 EP5 E3 wind turbines with a hub height of 166.0 m and an output of 5.56 MW each will be built in Lügde, Lügde.

Commissioning: 2024 / 2025
Manufacturer: Enercon GmbH
Number: 11 x Enercon-160 EP5 E3
Nominal output: 5.56 MW
Hub height: 166 m
Rotor Ø: 160 m

A total of 11 Enercon-160 EP5 E3 wind turbines with a hub height of 166.0 m and an output of 5.56 MW each will be built in Lügde, Lügde.

Current status:

The construction of wind turbines 3, 4, 5, 6, 7, 8, 9, 10, and 11 has been completed. The 11 wind turbines will be gradually commissioned shortly. The tower construction for wind turbine 11 is expected to be completed in calendar week 40. Max-Bögl has completed the first construction phase of the last two concrete towers (wind turbines 9 and 11). At the same time, the tower components (nacelle, hub, and generator) are being delivered to the respective locations. The first section of the tower construction is currently being carried out at WEA 8 and the concrete tower parts are being delivered to WEA 6. The first stages of construction for WEA 3, 4, 5, 7, and 10 have been completed. The first tower parts will be delivered to WEA 3 and WEA 4 in calendar weeks 44 and 45. The Max Bögl company from Sengenthal began construction of the foundations in calendar week 32. Construction of the access roads, access radii, and crane sites began in calendar week 26 of 2022. At the same time, sub-base layers and reinforcement work are being carried out.

Current work at the wind farm

Road construction: W. Koldewei GmbH 27252 Schwaförden
Foundation construction: Max Bögl 92369 Sengenthal

 

WTG 1
1st calendar week 00 > See Wörderfeld wind farm

WTG 2
1st calendar week 00 > See Wörderfeld wind farm

WTG 3
1. CW  26 > Road construction / crane positioning area / assembly areas under construction.
2. CW  32 > Installation of the cleanliness layer.
3. CW  32 > Reinforcement lower layer / anchor cage installation
4. CW  35 > Installation of reinforcement
5. CW  37 > Foundation construction completed
6. CW 21 >  Tower construction completed.

WTG 4
1. CW 26 > Road construction / crane positioning area / assembly areas under construction.
2. CW 33 > Installation of the cleanliness layer.
3. CW 33 > Reinforcement of the lower layer / positioning of the anchor cage
4. CW 37 > Foundation construction completed
5. CW 25 > Tower construction completed.

WTG 5
1. CW 26 > Road construction / crane positioning area / assembly areas under construction.
2. CW  32 > Installation of the cleanliness layer.
3. CW 32 > Reinforcement of lower layer / positioning of anchor cage.
4. CW 35 > Concreting the foundation.
5. CW 37 > Filling the foundation.
6. CW 19 > Tower construction completed.

WTG 6
1. CW 26 > Road construction / crane positioning area / assembly areas under construction.
2. CW 33 > Tower construction completed.

WTG 7
1. CW 26 > Road construction / Crane positioning area / Assembly areas under construction
2. CW 37 > Reinforcement construction
3. CW 38 > Concreting
4. CW 39 > Foundation construction completed.
5. CW 28 > Tower construction completed.

WTG 8
CW 26 > Road construction / crane site / assembly areas under construction.
CW 38 > Installation of the 10cm blinding layer
CW 31 > Tower construction completed.

WTG 9
CW 36 > Tower construction completed.

WTG 10
CW 32 > Road construction / crane positioning area / assembly areas under construction.
CW 37 > Installation of the saber layer / positioning of the anchor cage
CW 38 > Installation of the reinforcement
CW  39 > Concreting
CW 36 > Tower construction completed.

WTG 11
CW  41 > Tower construction completed.

 