Lügde Wind Farm

Lügde Wind Farm

A total of 11 Enercon-160 EP5 E3 wind turbines with a hub height of 166.0 m and an output of 5.56 MW each will be built in Lügde, Lügde.

Commissioning: 2024 / 2025
Manufacturer: Enercon GmbH
Number: 11 x Enercon-160 EP5 E3
Nominal output: 5.56 MW
Hub height: 166 m
Rotor Ø: 160 m

A total of 11 Enercon-160 EP5 E3 wind turbines with a hub height of 166.0 m and an output of 5.56 MW each will be built in Lügde, Lügde.

Current status:

The 1st stage of tower construction has been completed on WTG 3, 4 and WTG 7. The Max Bögl company from Sengenthal started building the foundations in week 32. Construction of the access roads, access radii and crane parking areas began in calendar week 26, 2022. At the same time, clean layers and reinforcement construction measures are being carried out.

Current work at the wind farm

Road construction: W. Koldewei GmbH 27252 Schwaförden
Foundation construction: Max Bögl 92369 Sengenthal

 

WTG 1
1st calendar week 00 > See Wörderfeld wind farm

WTG 2
1st calendar week 00 > See Wörderfeld wind farm

WTG 3
1. CW  26 > Road construction / crane positioning area / assembly areas under construction.
2. CW  32 > Installation of the cleanliness layer.
3. CW  32 > Reinforcement lower layer / anchor cage installation
4. CW  35 > Installation of reinforcement
5. CW  37 > Foundation construction completed
6. CW 48 > 1st stage tower construction completed.

WTG 4
1. CW 26 > Road construction / crane positioning area / assembly areas under construction.
2. CW 33 > Installation of the cleanliness layer.
3. CW 33 > Reinforcement of the lower layer / positioning of the anchor cage
4. CW 37 > Foundation construction completed
5. CW 49 > 1st stage tower construction completed.

WTG 5
1. CW 26 > Road construction / crane positioning area / assembly areas under construction.
2. CW  32 > Installation of the cleanliness layer.
3. CW 32 > Reinforcement of lower layer / positioning of anchor cage.
4. CW 35 > Concreting the foundation.
5. CW 37 > Filling the foundation.
6. CW 51 > Delivery of tower parts.

WTG 6
1. CW 26 > Road construction / crane positioning area / assembly areas under construction

WTG 7
1. CW 26 > Road construction / Crane positioning area / Assembly areas under construction
2. CW 37 > Reinforcement construction
3. CW 38 > Concreting
4. CW 39 > Foundation construction completed.
5. CW 51 > 1st stage tower construction completed.

WTG 8
CW 26 > Road construction / crane site / assembly areas under construction.
CW 38 > Installation of the 10cm blinding layer
CW 39 > Installation of the steel reinforcement

WTG 9
CW 38 > Road construction / crane positioning area / assembly areas under construction.

WTG 10
CW 32 > Road construction / crane positioning area / assembly areas under construction.
CW 37 > Installation of the saber layer / positioning of the anchor cage
CW 38 > Installation of the reinforcement
CW  39 > Concreting
CW 40 > Foundation construction completed

WTG 11
CW  37 > Road construction / crane positioning area / assembly areas under construction.

 

More info

Data & photos of our projects can be found here here.

You can find the latest news in the overview under News.