We are erecting 1 Enercon-175 EP5 wind turbine with a hub height of 162 m and an output of 6 MW in Kuppendorf, Kirchdorf municipality.
Commissioning:
Manufacturer: Enercon GmbH
Quantity: 1 x Enercon-175 EP5
Nominal output: 6 MW
Hub height: 162 m
Rotor Ø: 175 m
We are erecting 1 Enercon-175 EP5 wind turbine with a hub height of 162 m and an output of 6 MW in Kuppendorf, Kirchdorf municipality.
Current status:
On 16 December 2024, tower construction was completed. In week 39, the company Max Bögl completed the first phase of the tower assembly. Delivery of the concrete tower segments completed. The foundation work was completed in week 29. The development of the access roads, access radii and crane parking areas began in week 16, 2024.
Road construction: W. Koldewei GmbH 27252 Schwaförden
Tower construction: Max Bögl, 93269 Sengenthal
WTG 1
1. CW 30 > Backfilling & covering of foundation
2. CW 30 > LPD tests are carried out after foundation construction
3. CW 32 > Delivery of the concrete tower parts
4. CW 38 > Start of tower construction
5. CW 39 > 1st phase of tower construction completed.
6. CW 39 > Tower construction completed.