Kuppendorf wind farm
Kuppendorf wind farm
We are erecting 1 Enercon-175 EP5 wind turbine with a hub height of 162 m and an output of 6 MW in Kuppendorf, Kirchdorf municipality.
Commissioning:
Manufacturer: Enercon GmbH
Quantity: 1 x Enercon-175 EP5
Nominal output: 6 MW
Hub height: 162 m
Rotor Ø: 175 m
We are erecting 1 Enercon-175 EP5 wind turbine with a hub height of 162 m and an output of 6 MW in Kuppendorf, Kirchdorf municipality.
Current status:
In week 39, the company Max Bögl completed the first phase of the tower assembly. Delivery of the concrete tower segments completed. The foundation work was completed in week 29. The development of the access roads, access radii and crane parking areas began in week 16, 2024.
Road construction: W. Koldewei GmbH 27252 Schwaförden
Tower construction: Max Bögl, 93269 Sengenthal
WTG 1
week 25 > Reinforcement installation of the foundation
week 30 > Backfilling & covering of foundation
week 30 > LPD tests are carried out after foundation construction
week 32 > Delivery of the concrete tower parts
week 38 > Start of tower construction
week 39 > 1st phase of tower construction completed.